Bulk Sampling and Drilling Begin

Friday 14th December, 2015

Both the 1 tph DMS module and the “front end” (a crushing and screening section) of the mini-bulk sampling plant have now been received by the company’s Tabora office. The plant will be commissioned early in January, at which time delivery of the third, and final, component of the plant, the X-Ray recovery unit, is expected.

Collection of a bulk sample from the 5 Ha surface area Loya 1 kimberlite has started and drilling is underway on fifteen geophysical targets generated from the Ikungu Survey to the east of Tabora.

Work has begun on the field mapping of structures, derived from geophysical interpretation, believed to be suitable hosts for gold and base metals.